oil4
  • Project :
    GJOA
  • Agent / Client:
    Gillie & Blair
  • Workscope :
    Loading 2 x Tensioners
    (120T Each 7.4 * 5.75 * 5.75m / l * w * h)
  • Vessel:
    North Ocean 102 / 138m Draft 6.4m
  • Location :
    Under Radius of 250Ton SWL Dockside Crane – Shepherd Offshore – Offshore Technology Park – Walker – Newcastle
  • Date / Time Arrival :
    21/7/09 03:50hrs
    Date / Time Departure :
    21/7/09 13:40hrs

Shepherd Offshore Services Provided :

  • Storage
  • Fabrication solution
  • Heavy & Abnormal lifting services
  • Material handling solutions
  • Mob fast turnaround

Diagrams

Click Image To Enlarge Diagram
ap_tyne_drawing_150x150

Shepherd Offshore Comments:

Shepherd Offshore successfully achieved an efficient and difficult lifting/positioning/releasing sequence quay to vessel due to the ability and professionalism of the lifting teams and especially the crane driver.