Project:
MAM022
Agent/Clients/Third Parties:
Mammoet (UK) Ltd
Workscope:
Operation Type: Auxiliary discharge
Description of Scope: Discharge 1 x 128 ton transformer, and 33 ancillary items. Storing items and assemble of a twin 16-axle girder trailer.
Vessel:
EEMS Servant
Services provided:
- Pre-arrival Planning
- Pre-Arrival Set-up
- Lift Design Engineering
- Mobile Crane Support
- Mobilisation, Positioning and Set-up of Crane
- Complex Lifting Services
- Material Handling Solutions
- Storage Solutions
- Transportation Solutions
- Project Management
- Logistics Support
Testimonial:
Supervisor’s management, assistance, and communication: 5/5
Quayside operational personnel punctuality: 5/5
Quality of service received from the operations personnel: 5/5
Quayside set up & Housekeeping: 5/5
How would you rate our HSE performance? 5/5
Was the job done accurately against the scope? 5/5
Staff’s professionalism and aptitude: 5/5
Staff’s ability to communicate and provide quality support: 5/5
How will you rate our overall quality during the full work scope? 5/5
Would you be confident to recommend SOS to others? 5/5
“A big thanks to the Shepherd Offshore personal, for your assistance in ensuring that the delivery was able to depart on Saturday without any issues. The delivery went well, and the transformer is now being installed at the site.”
D Trigg, Project Manager, Mammoet
Shepherd Offshore Comments:
“Shepherd Offshore are delighted to have played an integral part in discharging a transformer which will be used for the national power grid operating in the North East at Stella West Power Station in Gateshead.
Working tirelessly, the team integrated well with Mammoet and were efficient and proactive in enabling a well planned and effective project. With planning and organising at the forefront for a safe, secure and time efficient project. “
General Manager, Shepherd Offshore